What is a SiGeKo? Germany’s construction safety coordinator explained
SiGeKo is the common German abbreviation for a safety and health coordinator on construction sites. Germany’s Construction Site Ordinance (BaustellV) itself uses the term “coordinator”. This guide explains what the term means, which duties section 3 BaustellV sets out for planning and execution, which competence RAB 30 describes and how the role differs from the construction client, employers and occupational safety specialists. Whether your project needs a coordinator is covered in the guide “When is a safety coordinator required?”. This guide concerns Germany.
SiGeKo editorial team · lol.marketing LLC · Updated
SiGeKo: meaning and abbreviation
SiGeKo stands for Sicherheits- und Gesundheitsschutzkoordinator, the safety and health coordinator. The abbreviation is widely used in practice; the Construction Site Ordinance uses the term “coordinator”. It refers to the person who coordinates safety and health between the parties on construction sites where employees of several employers work.
Under section 3(1) BaustellV, the person responsible under section 4 must appoint one or more suitable coordinators for construction sites where employees of several employers work. Under section 4, this is the construction client unless a third party is commissioned to take these measures on its own responsibility. The client or the commissioned third party may also perform the coordinator’s duties itself.
Important: under section 3(1a) BaustellV, appointing suitable coordinators does not release the construction client or the commissioned third party from its responsibility.
Coordinator duties while the execution is being planned
RAB 30 specifies the duties under section 3(2) BaustellV in more detail. For this phase it mentions, among other things, identifying safety-relevant interactions between trades, advising on site set-up and scheduling, promoting safety and health requirements in tender and contract documents and, where applicable, helping to prepare the advance notice.
Section 3(2) BaustellV lists three duties while the execution of the project is being planned:
- coordinate the measures under section 2(1) BaustellV – applying the general principles of section 4 ArbSchG when scheduling simultaneous or consecutive work and setting work durations,
- prepare the safety and health plan or have it prepared,
- compile a file with the safety and health information to be taken into account during possible later work on the structure.
Coordinator duties during execution
For execution, RAB 30 mentions as examples safety meetings and site inspections with documented and evaluated results, requesting evidence, and informing all contractors, including subcontractors and self-employed contractors, about the safety and health measures.
Under section 3(3) BaustellV, during execution the coordinator must:
- coordinate the application of the general principles of section 4 ArbSchG,
- ensure that employers and self-employed contractors fulfil their duties under the BaustellV,
- adapt the safety and health plan, or have it adapted, when changes in execution affect further coordination,
- organise cooperation between employers,
- coordinate the employers’ monitoring of the correct application of working procedures.
What competence does a coordinator need?
The BaustellV requires a “suitable” coordinator. RAB 30 describes what this involves: sufficient and relevant construction knowledge, occupational safety knowledge, specific coordinator knowledge and professional experience in planning and/or executing construction projects. Depending on the type and scale of the project, RAB 30 mentions at least two years of professional experience.
According to RAB 30, the knowledge required in a particular case depends on the type and scale of the project, the hazards involved and the phase in which the coordinator is engaged. The construction client or the commissioned third party selects the coordinator.
How the role differs from employers and safety specialists
The coordinator coordinates between the parties; the role does not take over each company’s occupational safety duties. Section 5 BaustellV requires employers to take the necessary safety measures during execution and, among other things, to take the coordinator’s instructions and the safety and health plan into account.
An occupational safety specialist (SiFa) is appointed by the employer under section 5 ASiG and supports that employer under section 6 ASiG. A coordinator, by contrast, is appointed for the construction project under the BaustellV and coordinates across individual employers. The two roles have different legal bases and duties.
How records support coordination
Many coordinator duties produce records: the safety and health plan, inspection reports, minutes of safety meetings, issues with actions and deadlines, and the file for later work. Software or templates can organise these records. They do not replace professional coordination, on-site judgement or the responsibilities of the parties involved.
Frequently asked questions
What does the abbreviation SiGeKo stand for?
Sicherheits- und Gesundheitsschutzkoordinator, the safety and health coordinator. The Construction Site Ordinance uses the term “coordinator”.
Who appoints the coordinator?
Under section 3(1) together with section 4 BaustellV, the construction client or a third party it commissions to take these measures on its own responsibility. Either may also perform the duties itself.
Is a coordinator the same as an occupational safety specialist?
No. Under the ASiG, an occupational safety specialist supports their employer. Under the BaustellV, a coordinator coordinates safety and health between the employers on a construction site.
Does every construction site need a coordinator?
No. Section 3(1) BaustellV links the appointment to sites where employees of several employers work. The guide “When is a safety coordinator required?” explains the assessment in detail.
Sources and professional context
- BaustellV section 3 – coordination
- BaustellV section 4 – appointment
- BaustellV section 2 – advance notice and safety and health plan
- BaustellV section 5 – employers’ duties
- BAuA – construction site safety rules (RAB 10, 30 and 31)
- ASiG section 5 – appointment of occupational safety specialists
- ASiG section 6 – duties of occupational safety specialists
These explanations concern Germany. Check the current source documents and the requirements of your specific project.
Related resources
When is a safety coordinator required in Germany?
Check when a German construction project needs a safety coordinator, advance notice and a safety and health plan, with thresholds and practical examples.
Read morePDF + editable fileSafety and health plan template: Excel, PDF and guidance
Free safety and health plan template with guidance and a fictional example. Organise trades, hazards, measures and dates for a German construction project.
Read the instructionsPDF + editable fileFree site inspection report template: Word and PDF
Site inspection report template for construction: record observations, photos, actions, owners and deadlines. Word and PDF without registration.
Read the instructionsPractical guidance · GermanyConstruction site advance notice in Germany: thresholds, deadline and content
When is construction site advance notice required under Germany’s BaustellV? Check thresholds, the two-week deadline, Annex I particulars, display and significant changes, with sources and a checklist.
Read more