Construction site advance notice in Germany: thresholds, deadline and content

Whether a construction site requires advance notice depends on the thresholds in section 2(2) of Germany’s Construction Site Ordinance (BaustellV). This guide explains the deadline, responsibility, minimum particulars, display and significant changes. For the separate question of appointing a safety coordinator, see the related guide below.

SiGeKo editorial team · lol.marketing LLC · Updated

When is construction site advance notice required?

Section 2(2) BaustellV provides two alternative thresholds. The first requires both the duration and simultaneous workforce thresholds to be exceeded. The person-day alternative applies independently of that combination.

Exactly 30 working days, exactly 20 simultaneous workers or exactly 500 person-days do not exceed the corresponding threshold. Still check the other alternative.

RAB 10 clarifies the terms: “simultaneously” means that at least 21 workers are scheduled to work on site at the same time for at least one shift. One person-day is the work of one person over one shift.

  • Work is expected to last more than 30 working days and more than 20 workers will be employed simultaneously, or
  • the expected volume of work exceeds 500 person-days.

Who submits the notice, when and to whom?

Under section 2(2), the person responsible under section 4 BaustellV must submit the notice. Section 4 names the construction client unless a third party has been appointed to carry out these measures on its own responsibility.

The notice must be submitted to the competent authority no later than two weeks before the site is established. This is the occupational safety authority of the relevant German federal state; its name differs from state to state. Establish which office is competent for your project.

According to RAB 10, establishing the site begins with the essential preparatory work on site, such as setting up welfare facilities, installing utilities or delivering materials and equipment. Count the two weeks back from that point.

What particulars does Annex I require?

Under section 2(2), the notice must include at least the particulars in Annex I. The following list translates those particulars from the German original:

  • Location of the construction site
  • Name and address of the construction client
  • Type of construction project
  • Name and address of the third party responsible in place of the construction client
  • Name and address of the coordinator
  • Expected start and expected duration of the work
  • Expected maximum number of workers on the construction site
  • Number of employers and self-employed contractors expected to work on the construction site
  • Details of the employers and self-employed contractors already selected

Display the notice and adapt it for significant changes

Section 2(2), second sentence, requires the person responsible under section 4 to display the notice visibly on site and adapt it for significant changes.

Under RAB 10, the notice is updated on site when significant changes occur; a renewed notification to the authority is not required. RAB 10 lists, for example, a change of construction client or coordinator, the first appointment of a coordinator, employees of several employers starting work for the first time, or a substantial increase in the number of simultaneous workers. The posted notice must remain legible throughout the work.

What follows from the advance notice requirement?

If advance notice is required and employees of several employers will work on site, section 2(3) requires the person responsible under section 4 to ensure that a safety and health plan is prepared before the site is established. The related plan template below includes completion guidance.

Where every worker works for the same employer and advance notice is required, section 2(4) requires the responsible person to ensure that this employer is informed before the site is established about the site circumstances that would need to be included in a plan under subsection 3, sentences 2 and 3.

Appointing a safety coordinator is a separate check. The related guide on when a coordinator is required addresses that question alongside advance notice and the safety and health plan.

Fictional calculation: 560 person-days

This example is entirely fictional: four workers are planned for 90 working days each in one phase, and eight workers for 25 working days each in another. The calculation is 4 × 90 + 8 × 25 = 360 + 200 = 560 person-days.

560 person-days exceed 500. In this fictional case, the second alternative in section 2(2) is therefore met, independently of the combination of more than 30 working days and more than 20 simultaneous workers.

Advance notice checklist

Use these steps as a working checklist for section 2(2) and Annex I:

  • Forecast the thresholds: check working days, simultaneous workforce and person-days.
  • Include the deadline of no later than two weeks before establishing the site in the programme.
  • Gather and compile the minimum Annex I particulars for submission.
  • Arrange for the notice to be displayed visibly on site.
  • Define a process for adapting the notice for significant changes.

Frequently asked questions

Must I resubmit the notice after changes?

No. Section 2(2) requires the notice to be adapted for significant changes. According to RAB 10, you update the notice posted on site; a renewed notification to the authority is not required.

Do exactly 500 person-days trigger advance notice?

The person-day alternative requires the expected volume to exceed 500 person-days. Exactly 500 do not meet that test. Still check the other alternative: more than 30 working days and more than 20 simultaneous workers.

Is an advance notice template available here?

This page provides the minimum Annex I particulars and a checklist, but no downloadable form of its own. A model advance notice form is included in BAuA’s RAB 10 as Annex A (see sources). Ask your competent authority whether it provides its own form.

Sources and professional context

These explanations concern Germany. Check the current source documents and the requirements of your specific project.